Capital & infrastructure
Vietnam’s building boom rests on private money
The 234 projects launched on 19 December 2025 carry a combined price of VND 3.4 quadrillion. The state budget will cover less than a fifth of it. Whether the remainder arrives will decide whether the government’s growth target is credible.
Nguyễn Đức Đạt11 min readKey takeaways
- 1The state budget funds about 18 percent of the VND 3.4 quadrillion (roughly $129 billion) programme. State-owned enterprises, banks, private developers and foreign investors are expected to provide the other 82 percent.
- 2Provincial administrations manage 157 of the 234 projects, which makes local authorities, not central ministries, the principal counterparty for investors.
- 3The Party’s target of at least 10 percent annual growth for 2026-30 is almost four points above the 2021-25 average, while investment has held at about 30 percent of GDP for a decade.
- 4Power is the largest single requirement. The revised PDP8 calls for $136.3 billion over 2026-30, including a more than thirtyfold increase in planned battery storage.
A programme launched in a morning
Ceremonies are a familiar instrument of Vietnamese policy, but the one held at 9:00 on 19 December 2025 was unusual in scale. In all 34 provinces and centrally run cities, officials broke ground on 148 projects and opened 86 more. The central event was staged in Hanoi, on the site of the planned Olympic Sports Urban Area.1
The timing, a month before the 14th National Party Congress, made the political purpose plain. The financial detail is more instructive. The Ministry of Construction valued the programme at more than VND 3.4 quadrillion, about $129 billion at the government’s conversion.1,2 How that sum is to be raised, and by whom, says more about the coming five years than the total itself.
Who pays
The state budget accounts for roughly VND 627 trillion, or 18 percent of the total. The remaining VND 2.79 quadrillion is classed as non-budget capital, a category that covers state-owned enterprises, commercial bank lending, domestic developers and foreign investors.1 The government, in other words, has committed to the programme while leaving most of its financing to balance sheets it does not directly control.
Figure 1
More than four-fifths of the December 2025 programme is funded outside the state budget
Funding of the 234 projects launched or opened on 19 December 2025, VND
- VND 2.79 quadrillion · 82%
- Non-budget capital (SOEs, banks, private and foreign investors)
- VND 627 trillion · 18%
- State budget
Source: Ministry of Construction, via the Government of Viet Nam portal1. USD conversion as reported by the government2.
Ownership is similarly dispersed. Provincial and municipal administrations manage 157 of the projects; corporations and SOEs hold 39, and central ministries 38.1 For an investor, the practical consequence is that the counterparty in most transactions will be a provincial authority, with its own capacity, priorities and procurement practice, rather than a ministry in Hanoi.
Figure 2
Provincial administrations manage two-thirds of the projects
Number of projects by managing body
- Local administrations157
- Corporations and SOEs39
- Ministries and agencies38
Source: Ministry of Construction, via the Government of Viet Nam portal1.
The government has committed to the programme while leaving most of its financing to balance sheets it does not directly control.
The growth arithmetic
The 14th Party Congress, which met in January 2026, set a target of average annual growth of at least 10 percent for 2026-30 and GDP per head of about $8,500 by 2030.3 On World Bank figures the economy grew by an average of about 6.2 percent a year in 2021-25, and it has not reached 10 percent in any year of the past decade.4
Figure 3
Growth has not reached the new target in any of the past eleven years
Real GDP growth, percent a year, 2015-25
Note: World Bank series. Vietnam’s National Statistics Office reports 8.02 percent for 2025 and 9.95 percent for the third quarter of 2026.
Source: World Bank, World Development Indicators4; target from the 14th Party Congress resolution3.
Momentum is building. Growth reached 8.02 percent in 2025 and 9.95 percent year on year in the third quarter of 2026, the fastest pace since 2022.6,7 Sustaining that pace for five years is a different proposition, and the binding constraint is investment. Gross fixed capital formation has hovered around 30 percent of GDP for a decade and eased to about 29 percent in 2024-25.5
Growth of 10 percent on a flat investment ratio would require a step change in the productivity of capital. The more plausible route is a higher investment ratio, and a programme that draws four-fifths of its funding from outside the budget shows where the government expects the additional capital to come from.
Figure 4
Investment as a share of GDP has drifted lower as the growth target has risen
Gross fixed capital formation, percent of GDP, 2010-25
Source: World Bank, World Development Indicators5.
Power is the largest claim
Energy is the largest single claim on that capital. The revised Power Development Plan 8, approved in April 2025, estimates investment needs of $136.3 billion for 2026-30: $118.2 billion for generation and $18.1 billion for transmission.8 The power plan alone exceeds the dollar value of the entire December programme.
Figure 5
Generation accounts for 87 percent of planned power investment
Revised PDP8 investment requirement, 2026-30, USD
- $118.2 billion · 87%
- Power generation
- $18.1 billion · 13%
- Transmission grid
Source: Decision 768/QĐ-TTg, as summarised by Vietnam Briefing8.
The composition of the plan matters as much as its size. Planned battery storage rises from 300 MW in the previous version to between 10,000 and 16,300 MW by 2030, and solar capacity from about 12.8 GW to between 46.5 and 73.4 GW.9 Storage and transmission are what allow new solar and wind output to reach demand in Hanoi and Ho Chi Minh City. They are also the assets with the least settled revenue models. In our view, it is there that the quality of project structuring will determine whether capital arrives on time.
- $136.3B
- Revised PDP8 investment requirement, 2026-30
- 30×+
- Increase in planned battery storage against the previous plan
- $18.1B
- Transmission investment over the same period
Foreign capital
Foreign investors have so far responded. Disbursed FDI rose for a fourth consecutive year in 2025, to an estimated $27.6 billion, the highest in five years; registered commitments reached $38.4 billion.10 More than four-fifths of disbursed capital, however, went to manufacturing. Infrastructure is competing for foreign money rather than receiving it by default.
Figure 6
Disbursed FDI has risen by 40 percent since 2021
Foreign direct investment disbursed in Viet Nam, USD billion
Note: The 2025 figure is a preliminary estimate.
Source: National Statistics Office, via The Investor10.
Portfolio flows may widen the pool. FTSE Russell confirmed in April 2026 that Vietnam would be reclassified from frontier to secondary emerging status from 21 September 2026.11 Local brokers expect $6-8 billion of net foreign inflows as index funds adjust their holdings.12 A deeper equity market would give developers and SOEs an alternative to bank credit, on which Vietnamese infrastructure has long depended.
What will decide the outcome
Four questions will determine how much of the programme is delivered on schedule. The first is disbursement. Vietnam’s public investment has often lagged its plans, and the measure that matters is how much of the non-budget share reaches financial close in 2026 and 2027.
The second is provincial capacity. With 157 projects in local hands, the quality of provincial preparation and procurement will separate bankable projects from announcements. The third is whether storage and grid assets acquire tariffs or contracts that lenders will accept; the implementing rules will matter more than the capacity targets. The fourth is finance for state-owned enterprises, which own many of the most capital-intensive assets and whose access to bonds, foreign lenders and equity partners will set the pace of delivery.
References
- 1.Government of Viet Nam (VGP). "Viet Nam to break ground, inaugurate 234 projects on December 19." December 2025. en.baochinhphu.vn
- 2.Viet Nam News. "PM told ministries to carefully prepare for major ceremony of 234 projects, worth over $129b." December 2025. vietnamnews.vn
- 3.Viet Nam News. "Việt Nam outlines ambitious growth and reform agenda in Party Congress’s resolution." January 2026. vietnamnews.vn
- 4.World Bank. World Development Indicators: GDP growth (annual %), Viet Nam (NY.GDP.MKTP.KD.ZG). Updated October 2026. data.worldbank.org
- 5.World Bank. World Development Indicators: Gross fixed capital formation (% of GDP), Viet Nam (NE.GDI.FTOT.ZS). Updated October 2026. data.worldbank.org
- 6.Viet Nam News. "Việt Nam records 8.02% GDP growth in 2025, 8.46% in Q4." January 2026, citing the National Statistics Office. vietnamnews.vn
- 7.VietnamPlus. "Vietnam posts GDP growth of 9.95% in Q3." October 2026, citing the National Statistics Office. en.vietnamplus.vn
- 8.Vietnam Briefing. "Vietnam Revises PDP8: Key Targets of the National Power Development Plan" (Decision 768/QĐ-TTg, 15 April 2025). vietnam-briefing.com
- 9.Watson Farley & Williams. "Vietnam makes major updates to Power Development Plan VIII." 2025. wfw.com
- 10.The Investor. "Vietnam’s 2025 FDI disbursement hits 5-year high." January 2026, citing the National Statistics Office. theinvestor.vn
- 11.The Investor. "FTSE Russell confirms Vietnam’s market status upgrade to secondary emerging from Sept 21." April 2026. theinvestor.vn
- 12.Voice of Vietnam. "FTSE Russell upgrades Vietnam’s stock market to secondary emerging market status." Estimates of foreign inflows from local securities firms. kynguyenvuonminh.vov.vn
Figures are drawn from the sources listed and were current at publication. Charts are redrawn by Corvus from the original data. This article is for information only and is not investment, legal, or tax advice.
Related analysis
- Vietnam’s new investment law trades permission for accountabilityThe 2025 Law on Investment cuts approvals at the outset and moves oversight to inspection afterwards.
- Vietnam’s power investors fear contracts more than currenciesPrivate power investment fell 96 percent in 2023 after pricing rules changed.